Reduce Construction Costs with Clash Detection Analysis

BIM & TechnologyMarch 10, 20242 min read
Reduce Construction Costs with Clash Detection Analysis

Clash Detection: Debugging in the Virtual Construction Site

One of the biggest cost items in construction projects is "Rework" costs. Discovering on-site that a ventilation duct collides with a steel beam causes work stoppage, material waste, and increased labor costs. BIM (Building Information Modeling) technology fundamentally solves this problem with **Clash Detection**.

Types of Clashes

We can discuss three types of clashes in a project:

1

**Hard Clash

** The physical intersection of two building elements.

* *Example:* A fire pipe passing through a column.

2

**Soft Clash (Clearance)

** Violation of the required space for assembly or maintenance of an element.

* *Example:* Insufficient distance in front of a valve for maintenance.

3

**Workflow Clash

** Timing errors during construction.

* *Example:* Trying to install pipes after a wall has been closed.

Cost Savings Analysis

Research (Penn State BIM Guide) shows that the cost of a clash increases logarithmically depending on which phase of the project it is detected.

Detection PhaseSolution Cost (Estimate)Impact Duration
Design (BIM)$20 - $50 (Engineer Hours)1 Hour
Tender / Procurement$500 - $1,000 (Revision)1 Day
Site (During Construction)$5,000+ (Removal, Materials, Delays)3-7 Days
Analitik Özet

Example Scenario: In a 50,000 m² industrial facility project, 1,500 hard clashes were detected and resolved at the design table through BIM coordination. If these errors had reached the site, they would have caused an average of 5%-10% deviation in the project budget.

Eos Proje Approach

At Eos Proje, we clash the "As-Built Model" produced through laser scanning with the "Design Model" (As-Designed). This way, we check not only the clashes between new systems but also the compatibility of new systems with the existing building.

Tools We Use:

Autodesk Navisworks: Advanced clash matrices and reporting.
BIM Track / BIMcollab: Assignment and tracking of issues to discipline managers.

Clash detection is not just a "bug finding" process; it is a process that guarantees the constructability of the project.